TONIGHT @7PM! Fight Bitcoin Mining on Seneca Lake

The Town of Torrey has referred the matter of expanding the Greenidge Power Plant (AKA Bitcoin Mine) to the Yates County Planning Board, which meets TONIGHT, January 28th at 7:00 pm. This referral is basically an admission by the Town Planning Board that it should have consulted the County Board originally, as required by Law prior to issuing the conditioned negative declaration and issuing the site permit. The Town must start the SEQR review process over and conduct a complete environmental review, including requiring DEC participation and a full Environmental Impact Statement.